Yolonda’s House Addition July 2020

Yolonda works at Casa and has a personal family matter requiring a room with bath attached to house.
Location will be in rear where the grade is steep.

Footers dug July 10
Pastor Abel teaching young men how to do rebar
Rebar installed in footing
Footers poured
July 14 started laying block
Wall ready for column pour.
Upper piers installed
Forms for slab installed

Rebar installed July 23
This man is using his head to deliver 50 bags of concrete
Yolonda’s Husband Pastor Angel on left and Pastor Abel on right who is helping on block and concrete
Pouring slab July 28, 2020
Next phase put up walls
Last update July 28, 2020